Diageo – Substation Upgrade

We firmly believe that prioritizing workplace safety is not only a core value but a critical factor contributing to organizational efficiency, competitiveness, and long-term stability.

Information About the Project

Project

Diageo – Substation Upgrade

Client

Diageo Canada Inc.

Scope of Work

  • Install customer supplied 6,000 amp switchgear E-House.
  • Supply, Install, and design 6,000 and 3,000 amp Cable buss Systems Remove and reinstall (2) 3 MVA Transformers.
  • Supply and maintain 800 kW generator.

Completion Date

Jan 1, 2021

Prime/Subcontractor

Prime-contractor

Location

Gimli, Manitoba